Placement AptitudeHardAMCAT · Wipro NLTH · Accenture pattern
A and B undertake a job for ₹5400. A alone can do it in 9 days and B alone in 12 days. With the help of C they finish it in 4 days. What is C's share of the payment if it is in proportion to work done?
- A. ₹1800
- B. ₹1350
- C. ₹600
- D. ₹1200
Correct answer: D. ₹1200
C's rate = 1/4 − 1/9 − 1/12 = (9 − 4 − 3)/36 = 1/18. In 4 days C does 4/18 = 2/9 of the job, so C gets 2/9 × 5400 = ₹1200. ₹1800 is an equal three-way split, but shares follow the work done.
Practise more Advanced Quantitative Ability (Placement) questionsAdvanced Quantitative Ability (Placement): notes and key points
More Advanced Quantitative Ability (Placement) questions
- The mirror image of a wall clock (reflected left to right) shows 4:35. What is the actual time on the clock?
- What is the smaller angle between the hour and minute hands of a clock at 7:20?
- A laptop is sold after two successive discounts of 20% and 10% on its list price. What single discount is equivalent to these two?
- 1 March of a certain year is a Monday. What day of the week is 1 April of the same year?
- A wall clock is set right at 6:00 a.m. on Monday. It loses 12 minutes every 24 hours, at a uniform rate. What time does it show at the…
- A can finish a project in 20 days and B in 30 days. They start together, but A leaves 5 days before the project is completed. In how many…