Cost and Management AccountingHard

The material price variance is generally the responsibility of the:

  1. A. Production manager
  2. B. Sales manager
  3. C. Foreman
  4. D. Purchase manager

Correct answer: D. Purchase manager

Price paid for materials is controlled by purchasing, whereas usage is controlled by production.