Budgeted fixed overhead is Rs 1,00,000 for 25 working days, but only 24 days are worked. The fixed overhead calendar variance is:
- A. Rs 1,000 Adverse
- B. Rs 4,000 Favourable
- C. Rs 2,000 Adverse
- D. Rs 4,000 Adverse
Correct answer: D. Rs 4,000 Adverse
Fixed overhead per day = 4,000. One day lost gives a calendar variance of Rs 4,000 Adverse.
Practise more Marginal & Standard Costing, Budgeting questionsMarginal & Standard Costing, Budgeting: notes and key points
More Marginal & Standard Costing, Budgeting questions
- Budgeted fixed overhead is Rs 50,000 for 10,000 hours. Actual hours worked are 9,500 and standard hours for actual output are 9,000. The…
- Normal selling price is Rs 100 with variable cost Rs 60. With idle capacity, a special order of 1,000 units is offered at Rs 70. The…
- A standard that assumes maximum efficiency with no wastage or idle time is called:
- Standard gang: 10 hours skilled at Rs 6 and 10 hours semi-skilled at Rs 4. Actual hours: skilled 12 and semi-skilled 8. The labour mix…
- Opening cash is Rs 50,000, receipts are Rs 3,00,000 and payments Rs 3,40,000. The firm wants a minimum balance of Rs 30,000. The amount to…
- In activity-based costing, overheads are assigned to products on the basis of: