Cost and Management AccountingHard
A standard that assumes maximum efficiency with no wastage or idle time is called:
- A. Ideal standard
- B. Normal standard
- C. Basic standard
- D. Current standard
Correct answer: A. Ideal standard
Ideal standards are attainable only under perfect conditions and are rarely used for control.
Practise more Marginal & Standard Costing, Budgeting questionsMarginal & Standard Costing, Budgeting: notes and key points
More Marginal & Standard Costing, Budgeting questions
- Standard gang: 10 hours skilled at Rs 6 and 10 hours semi-skilled at Rs 4. Actual hours: skilled 12 and semi-skilled 8. The labour mix…
- Opening cash is Rs 50,000, receipts are Rs 3,00,000 and payments Rs 3,40,000. The firm wants a minimum balance of Rs 30,000. The amount to…
- In activity-based costing, overheads are assigned to products on the basis of:
- In activity-based costing, a cost pool is:
- A set-up cost pool is Rs 1,20,000 for 120 set-ups. Product X has 40 set-ups and 2,000 units. Set-up cost per unit of X is:
- Sales are Rs 5,00,000, variable cost Rs 3,00,000 and fixed cost Rs 1,50,000. If sales rise by 20% (cost behaviour unchanged), profit is: