Cost and Management AccountingHard

Standard time is 4 hours per unit at Rs 15 per hour. 1,000 units were produced using 4,200 hours. The labour efficiency variance is:

  1. A. Rs 3,000 Favourable
  2. B. Rs 3,000 Adverse
  3. C. Rs 4,200 Adverse
  4. D. Rs 2,000 Adverse

Correct answer: B. Rs 3,000 Adverse

Standard hours = 4,000. Efficiency variance = (4,000 - 4,200) x 15 = Rs 3,000 Adverse.