Cost and Management AccountingHard

Standard for 2,000 units is 3 hours per unit at Rs 6 variable overhead per hour. Actual hours are 6,200 and actual variable overhead is Rs 37,820. The variable overhead expenditure variance is:

  1. A. Rs 1,200 Adverse
  2. B. Rs 1,820 Adverse
  3. C. Rs 620 Adverse
  4. D. Rs 620 Favourable

Correct answer: C. Rs 620 Adverse

Expected overhead on actual hours = 6,200 x 6 = 37,200. Actual is 37,820, so Rs 620 Adverse.