A flexible budget for 80% capacity has variable cost Rs 1,00,000 and fixed cost Rs 60,000. Total cost at 100% capacity is:

  1. A. Rs 2,00,000
  2. B. Rs 1,85,000
  3. C. Rs 1,60,000
  4. D. Rs 2,10,000

Correct answer: B. Rs 1,85,000

Variable cost at 100% = 1,00,000 x 100/80 = 1,25,000. Add fixed cost 60,000 to get Rs 1,85,000.