For actual output, standard hours are 400 at Rs 20 per hour. Actual hours paid are 420 at Rs 21 per hour. The total labour cost variance is:

  1. A. Rs 400 Adverse
  2. B. Rs 420 Adverse
  3. C. Rs 820 Adverse
  4. D. Rs 20 Adverse

Correct answer: C. Rs 820 Adverse

Standard cost = 8,000 and actual cost = 8,820. The difference is Rs 820 Adverse (rate 420 A plus efficiency 400 A).