Cost and Management AccountingHard
For actual output, standard hours are 400 at Rs 20 per hour. Actual hours paid are 420 at Rs 21 per hour. The total labour cost variance is:
- A. Rs 400 Adverse
- B. Rs 420 Adverse
- C. Rs 820 Adverse
- D. Rs 20 Adverse
Correct answer: C. Rs 820 Adverse
Standard cost = 8,000 and actual cost = 8,820. The difference is Rs 820 Adverse (rate 420 A plus efficiency 400 A).
Practise more Marginal & Standard Costing, Budgeting questionsMarginal & Standard Costing, Budgeting: notes and key points
More Marginal & Standard Costing, Budgeting questions
- Budgeted fixed overhead is Rs 1,20,000 for 6,000 units. Actual output is 5,500 units and actual fixed overhead is Rs 1,25,000. The fixed…
- Sales are Rs 4,00,000 and break-even sales are Rs 3,00,000. The margin of safety ratio is:
- Fixed cost is Rs 60,000, P/V ratio is 40% and the desired profit is Rs 30,000. The required sales are:
- Product A gives Rs 40 contribution per unit using 2 machine hours and product B gives Rs 60 using 4 hours. Machine hours available are…
- A favourable variance means that:
- The key principle of zero-based budgeting is that: