Cost and Management AccountingHard
Estimated total profit on a contract is Rs 2,00,000. Work certified is Rs 12,00,000 and contract price is Rs 15,00,000. Profit to be recognised on the basis of work certified to contract price is:
- A. Rs 1,20,000
- B. Rs 1,00,000
- C. Rs 1,60,000
- D. Rs 2,00,000
Correct answer: C. Rs 1,60,000
Work certified is 80% of contract price, so profit = 2,00,000 x 80% = Rs 1,60,000.
Practise more Cost Accounting Methods & Techniques questionsCost Accounting Methods & Techniques: notes and key points
More Cost Accounting Methods & Techniques questions
- 1,000 units are introduced, normal loss is 10%, 800 units are completed and 80 units remain in WIP at 50% conversion (materials fully…
- A job uses 25 machine hours at Rs 80 per hour, direct materials Rs 12,000 and direct labour Rs 6,000. If profit is 20% on selling price…
- In a cost-plus contract, the contractee pays the contractor:
- Inter-process profit arises in process costing when:
- A plant costing Rs 1,20,000 with scrap value Rs 20,000 and life of 5 years is used on a contract for 6 months. Depreciation charged to the…
- 5,000 units are processed at a total cost of Rs 1,37,000. Normal loss is 10% of input and is sold at Rs 4 per unit. Actual output is 4,600…