Cost and Management AccountingHard

Estimated total profit on a contract is Rs 2,00,000. Work certified is Rs 12,00,000 and contract price is Rs 15,00,000. Profit to be recognised on the basis of work certified to contract price is:

  1. A. Rs 1,20,000
  2. B. Rs 1,00,000
  3. C. Rs 1,60,000
  4. D. Rs 2,00,000

Correct answer: C. Rs 1,60,000

Work certified is 80% of contract price, so profit = 2,00,000 x 80% = Rs 1,60,000.