Cost and Management AccountingHard
An escalation clause in a construction contract:
- A. Penalises the contractor for delay
- B. Allows the contract price to be adjusted for changes in the cost of inputs
- C. Fixes the contractor's profit
- D. Provides for retention of money
Correct answer: B. Allows the contract price to be adjusted for changes in the cost of inputs
Such a clause adjusts the price when material or labour prices change beyond a stated limit.
Practise more Cost Accounting Methods & Techniques questionsCost Accounting Methods & Techniques: notes and key points
More Cost Accounting Methods & Techniques questions
- A batch of 500 units has set-up cost Rs 2,000, materials Rs 18,000, labour Rs 9,000 and overhead at 100% of labour. Cost per unit is:
- Budgeted overhead is Rs 4,80,000 for 24,000 labour hours. Actual hours are 22,500 and actual overhead is Rs 4,60,000. Overhead is:
- Running cost of a bus is Rs 4 per km and standing charges are Rs 30,000 a month. If it runs 6,000 km a month, the total cost per km is:
- Joint cost of Rs 3,00,000 is apportioned on NRV. A has sales Rs 4,00,000 and further cost Rs 80,000, B has sales Rs 2,00,000 and further…
- A's sales are Rs 6,00,000 and B's are Rs 4,00,000, with joint cost Rs 5,00,000 and further costs of Rs 1,00,000 for A and Rs 50,000 for B…
- The cost of rectifying normal defectives is generally charged to: