Cost and Management AccountingHard
Materials returned from the contract site to the stores are:
- A. Debited to the contract account
- B. Ignored
- C. Debited to the stores ledger control account only
- D. Credited to the contract account
Correct answer: D. Credited to the contract account
Materials returned reduce the cost of the contract, so the contract account is credited.
Practise more Cost Accounting Methods & Techniques questionsCost Accounting Methods & Techniques: notes and key points
More Cost Accounting Methods & Techniques questions
- Input is 2,000 units, normal loss 10% at the start (no scrap), completed units 1,500, closing WIP 200 units 60% converted (materials 100%)…
- In contract costing, work certified means:
- A school bus incurs Rs 72,000 a month, carries an average of 30 students and covers 2,400 km a month. Cost per student-km is:
- A contract is more than 50% complete. Notional profit is Rs 3,00,000 and cash received is 80% of work certified. Profit to be taken…
- Work done on a contract but not yet certified is valued at:
- In FIFO process costing, the cost per equivalent unit excludes: