Business LawsHard
The Coronation cases like Krell v Henry illustrate the doctrine of frustration under s.56 where
- A. Performance has become physically impossible
- B. The foundation of the contract is destroyed by a supervening event though performance remains literally possible
- C. The price has risen
- D. The parties disagree on terms
Correct answer: B. The foundation of the contract is destroyed by a supervening event though performance remains literally possible
Krell v Henry: the cancellation of the coronation procession destroyed the substratum of the contract; Indian courts apply s.56 similarly (Satyabrata Ghose v Mugneeram Bangur).
Practise more Business Laws (CA Foundation) questionsBusiness Laws (CA Foundation): notes and key points
More Business Laws (CA Foundation) questions
- Increased cost of performance due to a war-time closure of the Suez Canal making the route longer does not frustrate the contract, as held…
- A person who has received any advantage under an agreement later discovered to be void, or a contract that becomes void, must restore it…
- A, a friend, pays B's debt of Rs 5,000 to a creditor without B's request. B accepts the benefit. Under s.70 B
- B pays Rs 1,000 by mistake to C under the assumption of a debt. Under s.72, C
- A contracts to sell a flat to B for Rs 40 lakh. A breaches; the market price at the date of breach is Rs 46 lakh. B had paid no advance…
- In Hadley v Baxendale, a mill-owner's crankshaft broke and was delayed in transit due to the carrier's default. The mill-owner claimed…