Section 56 of the Indian Contract Act applies where the performance becomes impossible after the contract is made, and the contract becomes void. In such a case the party who has received an advantage must

  1. A. Restore it or make compensation for it to the person from whom he received it (s.65)
  2. B. Pay interest only
  3. C. Pay penalty
  4. D. Retain it

Correct answer: A. Restore it or make compensation for it to the person from whom he received it (s.65)

S.65 operates when a contract becomes void under s.56; restitution is due.