Business LawsHard
Section 56 of the Indian Contract Act applies where the performance becomes impossible after the contract is made, and the contract becomes void. In such a case the party who has received an advantage must
- A. Restore it or make compensation for it to the person from whom he received it (s.65)
- B. Pay interest only
- C. Pay penalty
- D. Retain it
Correct answer: A. Restore it or make compensation for it to the person from whom he received it (s.65)
S.65 operates when a contract becomes void under s.56; restitution is due.
Practise more Business Laws (CA Foundation) questionsBusiness Laws (CA Foundation): notes and key points
More Business Laws (CA Foundation) questions
- A agrees to sell his car to B for Rs 5 lakh on 10 April. B pays Rs 50,000 as advance. On 10 April the market price rises to Rs 5.6 lakh…
- A agrees to pay Rs 5,000 as damages in case of breach of a contract worth Rs 1 lakh; actual loss from breach is Rs 3,000. Under s.74 the…
- Where a party sues for breach of contract but the loss cannot be proved with certainty, the court under s.74 may award
- A bailee finds that the goods bailed were damaged in a fire which broke out in his godown despite ordinary prudence. Under s.151 and…
- A watch is deposited with a jeweller for repairs. After repairs, the owner refuses to pay the charges. The jeweller's right is
- A person makes a general pledge of goods by a mercantile agent who has the goods but not the owner's consent to pledge. Under s.178, the…