Behavioural CompetencyHard

A supply-chain client asks Nikhil to add a new report that is not in the signed scope, saying it is 'a small thing' and promising a good review. The project is already at 95% utilisation. What is the BEST course of action?

  1. A. Add it quietly since the client relationship matters more than the contract, because the team is under pressure already
  2. B. Decline outright because it is not in the signed scope, since that has worked on earlier projects
  3. C. Say you will assess the effort, log it as a change request with Ajay the delivery manager, and agree impact on cost and schedule before work starts
  4. D. Agree verbally now and sort out the paperwork after delivery, to keep things moving for everyone

Correct answer: C. Say you will assess the effort, log it as a change request with Ajay the delivery manager, and agree impact on cost and schedule before work starts

Routing through change control keeps the relationship positive while protecting scope, schedule and revenue; unlogged additions cause overruns and disputes.