Behavioural CompetencyVery hard
Lakshmi sees that the project is being run with a third of remaining members of the offshore team who are on leave for an extended festival, and the plan assumed full strength. What is the BEST course of action?
- A. Hope the team catches up after the festival
- B. Raise the capacity gap with the manager, re-plan the scope or timeline with options, and brief the client early
- C. Add extra work to those present without telling
- D. Wait for the client to notice delays
Correct answer: B. Raise the capacity gap with the manager, re-plan the scope or timeline with options, and brief the client early
Early re-planning with the client avoids surprises; overloading colleagues or waiting hides a foreseeable risk.
Practise more Behavioural Competency (Capgemini) questionsBehavioural Competency (Capgemini): notes and key points
More Behavioural Competency (Capgemini) questions
- Your mentee Vikram makes the same merge conflict mistake for the third time in a week despite earlier explanations. You are short on time…
- Ananya receives a request from a colleague in another business unit for revenue data, saying it would help the benchmarking but the…
- Rohan is asked to train a client's new hire on the reporting tool, but Rohan's own project is stretched and the training has not been…
- Pooja receives a performance review saying communication with stakeholders is weak, but Pooja thinks the confusing hand-over example cited…
- The client's team asks Ananya for a dump of claims to 'analyse trends'. Ananya knows the data includes fields containing medical codes…
- Kavya learns that a data-centre network zone that the project relies on will be migrated next month, with no communication to the project…