Behavioural CompetencyHard
Kavya learns that a data-centre network zone that the project relies on will be migrated next month, with no communication to the project team yet. What is the BEST course of action?
- A. Wait for official notice before doing anything
- B. Alert your manager and the infrastructure contact, ask for the plan and assess the impact to the project risks
- C. Tell the client the project is at risk now
- D. Start redesigning the system on your own
Correct answer: B. Alert your manager and the infrastructure contact, ask for the plan and assess the impact to the project risks
Early inquiry with the right owners yields facts for the risk register; waiting or alarming the client without facts is premature.
Practise more Behavioural Competency (Capgemini) questionsBehavioural Competency (Capgemini): notes and key points
More Behavioural Competency (Capgemini) questions
- Imran is preparing a deliverable for the client and finds a rounding choice that makes the benchmark look better than reality, but is…
- Pooja sees Shreya in the shared office using a client-supplied laptop to browse personal sites and download free tools. What is the BEST…
- Ananya notices that the project has no documented rollback plan for next week's go-live. The manager Ritu says the team has done this…
- Divya finds a defect close to the release deadline of a mobile app that affects a reporting field. The project manager Deepa suggests…
- Kavya accidentally emails a spreadsheet containing identity document personal data of 120 customers to the wrong external domain. No one…
- Vikram discovers that the onboarding requirements document says one thing, while the client's product owner said something different in…