Behavioural CompetencyHard
Rohan learns that a data-centre storage array that the project relies on will be migrated next month, with no communication to the project team yet. What is the BEST course of action?
- A. Wait for official notice before doing anything, to keep things moving for everyone
- B. Tell the client the project is at risk now, because the team is under pressure already
- C. Alert your manager and the infrastructure contact, ask for the plan and assess the impact to the project risks
- D. Start redesigning the system on your own, since that has worked on earlier projects
Correct answer: C. Alert your manager and the infrastructure contact, ask for the plan and assess the impact to the project risks
Early inquiry with the right owners yields facts for the risk register; waiting or alarming the client without facts is premature.
Practise more Behavioural Competency (Capgemini) questionsBehavioural Competency (Capgemini): notes and key points
More Behavioural Competency (Capgemini) questions
- Nikhil realises midway through a documentation task that the estimate was too low and the work will overrun by two days. The task is not…
- Aarav accidentally emails a spreadsheet containing identity document personal data of 120 customers to the wrong external domain. No one…
- A banking client asks Rahul to add a extra user role that is not in the signed scope, saying it is 'a small thing' and promising a good…
- The client changes the UI design for the third time in two weeks. Siddharth's team is exhausted, the budget is nearly spent, and the…
- Rahul, an offshore analyst, is asked by the onsite coordinator to share daily progress updates three times a day, which Rahul finds…
- Imran finds a defect close to the release deadline of a payment patch that affects edge-case dates. The project manager Gaurav suggests…