Behavioural CompetencyHard
During sprint planning for a utilities engagement, Arjun believes the estimate Gaurav gave for the payment module is half of what it will really take. The client project manager is in the room and the team is nodding along. What is the BEST course of action?
- A. Say politely that your own estimate differs, share the assumptions behind it, and propose a short spike or breakdown to settle the number
- B. Stay silent in the meeting and tell Gaurav afterwards that the estimate looks unrealistic, to keep things moving for everyone
- C. Accept the estimate and plan to put in extra hours if it overruns, because the team is under pressure already
- D. Challenge Gaurav directly in front of the client and ask for the estimate to be redone, since that has worked on earlier projects
Correct answer: A. Say politely that your own estimate differs, share the assumptions behind it, and propose a short spike or breakdown to settle the number
Surfacing the gap with evidence and a way to resolve it protects the plan without embarrassing Gaurav; silence or heroic overtime hides a delivery risk until it is costly.
Practise more Behavioural Competency (Capgemini) questionsBehavioural Competency (Capgemini): notes and key points
More Behavioural Competency (Capgemini) questions
- Vikram receives an email that appears to be from the CEO asking to urgently buy ₹50,000 gift cards for a client and send the codes, saying…
- Sneha is on leave when a API timeout issue arises, and the client calls Sneha's personal phone. The backup, Mansi, is reachable but the…
- Rohan is offered a conference ticket by a vendor shortly before the vendor's training contract is up for renewal, which Rohan helps…
- Divya realises midway through a migration task that the estimate was too low and the work will overrun by two days. The task is not on the…
- A colleague Nandini confides in Tanvi that Nandini is struggling with a health condition and falling behind on the release. Nandini asks…
- The client asks Rohan to speed up the hotfix by disabling the encryption check in production temporarily. The client's own engineer…