Behavioural CompetencyHard
Divya realises midway through a migration task that the estimate was too low and the work will overrun by two days. The task is not on the critical path, and the team lead Deepa is in meetings all day. What is the BEST course of action?
- A. Wait until the overrun becomes certain before telling anyone
- B. Message Deepa now with the reason, the revised estimate and options to recover, rather than waiting for a meeting gap
- C. Cut testing steps to bring the work back to the original date
- D. Absorb the overrun by working late and mention it at the weekly review
Correct answer: B. Message Deepa now with the reason, the revised estimate and options to recover, rather than waiting for a meeting gap
A short written heads-up lets the lead plan around the slip even if not on the critical path; cutting tests or hiding it trades a visible delay for hidden risk.
Practise more Behavioural Competency (Capgemini) questionsBehavioural Competency (Capgemini): notes and key points
More Behavioural Competency (Capgemini) questions
- A colleague Nandini confides in Tanvi that Nandini is struggling with a health condition and falling behind on the release. Nandini asks…
- The client asks Rohan to speed up the hotfix by disabling the encryption check in production temporarily. The client's own engineer…
- During sprint planning for a insurance engagement, Pooja believes the estimate Jyoti gave for the single sign-on rollout is half of what…
- Kabir sees that the project is being run with only half remaining members of the offshore team who are on leave for an extended festival…
- Kabir, an offshore analyst, is asked by the onsite coordinator to share daily progress updates three times a day, which Kabir finds…
- A production issue in a banking client's nightly batch is traced to a change Vikram deployed that afternoon. The client has not yet…