Kabir sees that the project is being run with only half remaining members of the offshore team who are on leave for an extended festival, and the plan assumed full strength. What is the BEST course of action?

  1. A. Raise the capacity gap with the manager, re-plan the scope or timeline with options, and brief the client early
  2. B. Hope the team catches up after the festival, since that has worked on earlier projects
  3. C. Add extra work to those present without telling, to keep things moving for everyone
  4. D. Wait for the client to notice delays, because the team is under pressure already

Correct answer: A. Raise the capacity gap with the manager, re-plan the scope or timeline with options, and brief the client early

Early re-planning with the client avoids surprises; overloading colleagues or waiting hides a foreseeable risk.