Civil EngineeringHard
A rectangular sedimentation tank 25 m × 5 m × 3 m deep treats 4000 m³/day. The detention time is
- A. 0.09 h
- B. 256.00 h
- C. 2.25 h
- D. 0.75 h
Correct answer: C. 2.25 h
t = V/Q = 375/4000 day = 2.25 h.
Practise more Hydraulics, Irrigation & Environmental Engineering (Civil) questionsHydraulics, Irrigation & Environmental Engineering (Civil): notes and key points
More Hydraulics, Irrigation & Environmental Engineering (Civil) questions
- A rectangular sedimentation tank 20 m × 6 m × 3 m deep treats 4000 m³/day. The detention time is
- A rapid sand filter plant treats 10 MLD at a filtration rate of 6 m/h. The total filter area required (ignoring backwash downtime) is
- A rapid sand filter plant treats 15 MLD at a filtration rate of 5 m/h. The total filter area required (ignoring backwash downtime) is
- To disinfect 5000 m³ of water at a chlorine dose of 3 mg/L using bleaching powder with 30% available chlorine, the mass of bleaching…
- To disinfect 2000 m³ of water at a chlorine dose of 5 mg/L using bleaching powder with 30% available chlorine, the mass of bleaching…
- A chlorine dose of 3.5 mg/L leaves a residual of 0.5 mg/L after the contact time. The chlorine demand of the water is