Civil EngineeringVery hard
By Webster's method, for total lost time L = 10 s per cycle and critical flow ratios 0.15, 0.1, 0.18, the optimum cycle time is
- A. 46.5 s
- B. 35.1 s
- C. 11.4 s
- D. 26.3 s
Correct answer: B. 35.1 s
Y = 0.43; C0 = (1.5L+5)/(1−Y) = 20.0/0.57 = 35.1 s.
Practise more Transportation, Surveying & Estimation (Civil) questionsTransportation, Surveying & Estimation (Civil): notes and key points
More Transportation, Surveying & Estimation (Civil) questions
- A two-phase signal has lost time 16 s per cycle and critical flow ratios 0.3 and 0.2. With Webster's cycle time, the effective green time…
- A two-phase signal has lost time 12 s per cycle and critical flow ratios 0.3 and 0.2. With Webster's cycle time, the effective green time…
- An hourly count is 300 cars, 40 buses, 50 trucks and 200 two-wheelers. Taking PCU values car 1, bus 3, truck 3, two-wheeler 0.5, the…
- Spot speeds of four vehicles are 40, 60, 45, 70 km/h. The space-mean speed is
- In a CBR test the load at 2.5 mm penetration is 9.27 kN (standard loads: 13.24 kN at 2.5 mm and 19.96 kN at 5.0 mm). The CBR value based…
- Using the fourth-power law with a standard single axle load of 8.16 t, the equivalent axle load factor of a 16.00 t single axle is