A material is used at a maximum of 40, normal 35 and minimum 30 units per week. Lead time: maximum 8 weeks, minimum 2 weeks (normal 5 weeks). Reorder quantity is 900 units. The maximum level is:

  1. A. 985 units
  2. B. 1220 units
  3. C. 1045 units
  4. D. 1160 units

Correct answer: D. 1160 units

Reorder level = max usage x max lead = 320; minimum = ROL - normal usage x normal lead = 145; maximum = ROL + ROQ - min usage x min lead = 1160; average = 652.5.