AccountingHard

Budgeted factory overhead is Rs 1,20,000 for 10000 machine hours. Actual overhead incurred was Rs 1,50,000 for 6000 machine hours. Overhead absorbed at the pre-determined rate and the result are:

  1. A. Rs 78,000 over-absorbed
  2. B. Rs 78,000 under-absorbed
  3. C. Rs 30,000 under-absorbed
  4. D. Rs 48,000 under-absorbed

Correct answer: B. Rs 78,000 under-absorbed

Rate = 120000/10000 = 12/hr; absorbed = 12 x 6000 = 72000; actual 150000; under-absorbed by 78000.