AccountingHard
Budgeted factory overhead is Rs 2,50,000 for 50000 machine hours. Actual overhead incurred was Rs 2,40,000 for 52000 machine hours. Overhead absorbed at the pre-determined rate and the result are:
- A. Rs 20,000 under-absorbed
- B. Rs 10,000 over-absorbed
- C. Rs 20,000 over-absorbed
- D. Rs 22,000 over-absorbed
Correct answer: C. Rs 20,000 over-absorbed
Rate = 250000/50000 = 5/hr; absorbed = 5 x 52000 = 260000; actual 240000; over-absorbed by 20000.
Practise more Fundamentals of Financial & Cost Accounting (CMA Foundation) questionsFundamentals of Financial & Cost Accounting (CMA Foundation): notes and key points
More Fundamentals of Financial & Cost Accounting (CMA Foundation) questions
- Cash book shows a bank balance of Rs 71,000 (debit). Reconciling items: bank charges Rs 7,000 debited by the bank not yet recorded…
- A material is used at a maximum of 70, normal 50 and minimum 30 units per week. Lead time: maximum 6 weeks, minimum 2 weeks (normal 4…
- Budgeted factory overhead is Rs 2,70,000 for 20000 machine hours. Actual overhead incurred was Rs 2,50,000 for 25000 machine hours…
- A bill of Rs 4,60,000 discounted at 9% p.a. for the unexpired 4 months was dishonoured on maturity; the bank charged noting charges of Rs…
- The average adjusted profit of a firm is Rs 1,80,000, capital employed Rs 5,70,000 and the normal rate of return 8%. Goodwill at 4 years'…
- A product sells at Rs 25 with variable cost Rs 8 per unit; fixed costs are Rs 1,70,000. The break-even sales value is: