AccountingHard

Budgeted factory overhead is Rs 2,70,000 for 20000 machine hours. Actual overhead incurred was Rs 2,50,000 for 25000 machine hours. Overhead absorbed at the pre-determined rate and the result are:

  1. A. Rs 87,500 over-absorbed
  2. B. Rs 67,500 over-absorbed
  3. C. Rs 87,500 under-absorbed
  4. D. Rs 20,000 over-absorbed

Correct answer: A. Rs 87,500 over-absorbed

Rate = 270000/20000 = 13.5/hr; absorbed = 13.5 x 25000 = 337500; actual 250000; over-absorbed by 87500.