Budgeted factory overhead is Rs 1,70,000 for 25000 machine hours. Actual overhead incurred was Rs 1,80,000 for 30000 machine hours. Overhead absorbed at the pre-determined rate and the result are:

  1. A. Rs 10,000 under-absorbed
  2. B. Rs 24,000 under-absorbed
  3. C. Rs 24,000 over-absorbed
  4. D. Rs 34,000 over-absorbed

Correct answer: C. Rs 24,000 over-absorbed

Rate = 170000/25000 = 6.8/hr; absorbed = 6.8 x 30000 = 204000; actual 180000; over-absorbed by 24000.