Four periodic tasks (computation time C, period T = relative deadline), all released at t = 0, are scheduled by preemptive rate-monotonic scheduling: T1 (1, 4), T2 (2, 6), T3 (2, 12), T4 (5, 30). What is the worst-case response time of T4?

  1. A. 10
  2. B. 23
  3. C. 11
  4. D. 25

Correct answer: B. 23

Response-time analysis: R = C4 + sum over higher-priority tasks of ceil(R/Tj) x Cj, iterated from R = C4 until it stops changing (it converges at 23). One iteration only gives 11, and adding all computation times gives 10 (ignoring repeated preemptions).