A project's critical path has four activities with three-point estimates (optimistic, most likely, pessimistic) in weeks: (2, 4, 6), (3, 5, 13), (1, 3, 5) and (4, 6, 8). Using PERT (mean = (a + 4m + b)/6, variance = ((b - a)/6)^2, normal approximation, other paths ignored), what is the probability of finishing within 20 weeks?

  1. A. About 69%
  2. B. About 31%
  3. C. About 50%
  4. D. About 84%

Correct answer: A. About 69%

Means: 4, 6, 3, 6, total 19 weeks. Variances: (4/6)^2 = 0.444, (10/6)^2 = 2.778, 0.444, 0.444, total 4.111, so the standard deviation is 2.03 weeks (variances add along the path; standard deviations do not). z = (20 - 19)/2.03 = 0.49, and P(Z ≤ 0.49) = about 0.69. 31% is the probability of overrunning, 50% would be the deadline at the mean, and 84% corresponds to z = 1. Adding the four standard deviations instead (3.67 weeks, z = 0.27) is a further trap.