CS FundamentalsVery hardProduct company interview · GATE level
A project's critical path has four activities with three-point estimates (optimistic, most likely, pessimistic) in weeks: (2, 4, 6), (3, 5, 13), (1, 3, 5) and (4, 6, 8). Using PERT (mean = (a + 4m + b)/6, variance = ((b - a)/6)^2, normal approximation, other paths ignored), what is the probability of finishing within 20 weeks?
- A. About 69%
- B. About 31%
- C. About 50%
- D. About 84%
Correct answer: A. About 69%
Means: 4, 6, 3, 6, total 19 weeks. Variances: (4/6)^2 = 0.444, (10/6)^2 = 2.778, 0.444, 0.444, total 4.111, so the standard deviation is 2.03 weeks (variances add along the path; standard deviations do not). z = (20 - 19)/2.03 = 0.49, and P(Z ≤ 0.49) = about 0.69. 31% is the probability of overrunning, 50% would be the deadline at the mean, and 84% corresponds to z = 1. Adding the four standard deviations instead (3.67 weeks, z = 0.27) is a further trap.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A project has a budget at completion (BAC) of ₹400 lakh. At the end of month 5 the planned value is ₹180 lakh, the earned value ₹150 lakh…
- Under Musa's basic execution-time model, failure intensity falls linearly with failures experienced: λ(μ) = λ0 (1 - μ/ν0), and over…
- Defects injected: 40 during requirements, 60 during design and 100 during coding. A requirements review removes 50% of the defects present…
- A class has fields a, b, c, d, e and methods m1 (uses a, b), m2 (uses b, c), m3 (uses d) and m4 (uses d, e). Using the Chidamber-Kemerer…
- main has commits A-B-C-D-E (E is main's tip). feature was created at C and got commits F and G; then main was merged into feature…
- A service runs on 3 identical servers, each 95% available and failing independently; it works when at least 2 of the 3 are up (a majority…