CS FundamentalsVery hardProduct company interview · GATE level
A Kanban team has on average 24 work items in progress and completes 8 items per week. By Little's law, what is the average lead time? If throughput stays the same, what WIP limit would bring the average lead time down to 2 weeks?
- A. 3 weeks; a WIP limit of 16
- B. 3 weeks; a WIP limit of 12
- C. 0.33 weeks; a WIP limit of 16
- D. 3 weeks; a WIP limit of 8
Correct answer: A. 3 weeks; a WIP limit of 16
Little's law: average WIP = throughput x average lead time, so lead time = 24 / 8 = 3 weeks. For 2 weeks at 8 items per week, WIP must be 8 x 2 = 16. This is why Kanban limits work in progress: with throughput unchanged, less WIP means each item waits less. 0.33 weeks divides the wrong way round; 12 halves the WIP for a one-third cut in lead time.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A triple modular redundancy (TMR) design runs three identical modules and a voter that outputs the majority. Each module has reliability…
- A project's unadjusted function point count is 250. After the 14 general system characteristics are rated (0-5 each), the adjusted count…
- A system has 200 unadjusted function points. Using the IFPUG value adjustment factor (14 characteristics, each rated 0 to 5), what is the…
- Basic COCOMO for an embedded-mode project uses Effort = 3.6 x KLOC^1.20 person-months and Time = 2.5 x Effort^0.32 months. For a 50 KLOC…
- In basic COCOMO, embedded-mode effort grows as KLOC^1.20. If the size of an embedded project doubles, what happens to effort and to…
- A late project's team grows from 5 to 8 developers. By how many do the possible pairwise communication channels increase, the effect…