A Kanban team has on average 24 work items in progress and completes 8 items per week. By Little's law, what is the average lead time? If throughput stays the same, what WIP limit would bring the average lead time down to 2 weeks?

  1. A. 3 weeks; a WIP limit of 16
  2. B. 3 weeks; a WIP limit of 12
  3. C. 0.33 weeks; a WIP limit of 16
  4. D. 3 weeks; a WIP limit of 8

Correct answer: A. 3 weeks; a WIP limit of 16

Little's law: average WIP = throughput x average lead time, so lead time = 24 / 8 = 3 weeks. For 2 weeks at 8 items per week, WIP must be 8 x 2 = 16. This is why Kanban limits work in progress: with throughput unchanged, less WIP means each item waits less. 0.33 weeks divides the wrong way round; 12 halves the WIP for a one-third cut in lead time.