Basic COCOMO for an embedded-mode project uses Effort = 3.6 x KLOC^1.20 person-months and Time = 2.5 x Effort^0.32 months. For a 50 KLOC project, which estimate is correct?

  1. A. About 146 person-months over about 16.6 months
  2. B. About 240 person-months over about 17.0 months
  3. C. About 394 person-months over about 16.9 months, i.e. about 23 people on average
  4. D. About 394 person-months over about 23.3 months, i.e. about 17 people on average

Correct answer: C. About 394 person-months over about 16.9 months, i.e. about 23 people on average

E = 3.6 x 50^1.2 ≈ 393.6 PM and D = 2.5 x 393.6^0.32 ≈ 16.9 months, so average staff ≈ 393.6/16.9 ≈ 23. 146 and 240 PM are the organic and semi-detached figures; the last option swaps time and staff.