A project has budget at completion ₹200 lakh. To date: planned value ₹90 lakh, earned value ₹80 lakh, actual cost ₹100 lakh. What cost performance must the remaining work achieve to finish within the original budget (the to-complete performance index)?
- A. 0.80
- B. 1.10
- C. 1.20
- D. 1.25
Correct answer: C. 1.20
TCPI = (BAC - EV)/(BAC - AC) = (200 - 80)/(200 - 100) = 1.20. 0.80 is the current CPI, 1.25 its reciprocal, and 1.10 wrongly uses PV in place of EV.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A server has a mean time between failures of 500 hours. To meet a 99.8% availability target, what is the largest mean time to repair it…
- Use case points: actors - 2 simple (weight 1), 2 average (2), 3 complex (3); use cases - 5 simple (5), 8 average (10), 3 complex (15)…
- Henry and Kafura's information-flow complexity of a procedure is length x (fan-in x fan-out)^2. A 20-line procedure is called by 3…
- A package has 6 classes outside it depending on it (afferent coupling Ca = 6) and depends on 2 outside classes (efferent coupling Ce = 2)…
- In COCOMO's maintenance model, annual maintenance effort = annual change traffic (ACT) x development effort. A system took 120…
- Activities (days; predecessors): A 3 (-), B 4 (A), C 2 (A), D 5 (B), E 3 (C), F 2 (D, E). What are the total float and the free float of…