CS FundamentalsHardAccenture · Capgemini · PMP-style

A project has budget at completion ₹200 lakh. To date: planned value ₹90 lakh, earned value ₹80 lakh, actual cost ₹100 lakh. What cost performance must the remaining work achieve to finish within the original budget (the to-complete performance index)?

  1. A. 0.80
  2. B. 1.10
  3. C. 1.20
  4. D. 1.25

Correct answer: C. 1.20

TCPI = (BAC - EV)/(BAC - AC) = (200 - 80)/(200 - 100) = 1.20. 0.80 is the current CPI, 1.25 its reciprocal, and 1.10 wrongly uses PV in place of EV.