CS FundamentalsModerateGATE CS · Infosys
In COCOMO's maintenance model, annual maintenance effort = annual change traffic (ACT) x development effort. A system took 120 person-months to build and 15% of its code is expected to change each year. What is the annual maintenance effort?
- A. 8 person-months
- B. 15 person-months
- C. 13.8 person-months
- D. 18 person-months
Correct answer: D. 18 person-months
AME = ACT x SDE = 0.15 x 120 = 18 person-months a year. 8 divides 120 by 15 and 15 confuses the percentage with person-months.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Activities (days; predecessors): A 3 (-), B 4 (A), C 2 (A), D 5 (B), E 3 (C), F 2 (D, E). What are the total float and the free float of…
- A product backlog has 210 story points left. The team's velocity has ranged between 25 and 35 points per sprint. What is the honest range…
- A 6-member team plans a 10-working-day sprint at 6 focus hours per person per day. One member is on leave for 3 days and another for 2…
- In a quarter a team made 40 production deployments. 6 of them caused incidents needing a fix or rollback, and restoring service took 9…
- A team wants estimates from several experts without anchoring on the loudest voice. A coordinator collects anonymous estimates, shares the…
- A program has 240 executable statements and the current suite covers 180 of them. A new test executes 40 statements, 25 of which were…