CS FundamentalsModerateAccenture · Capgemini

A 6-member team plans a 10-working-day sprint at 6 focus hours per person per day. One member is on leave for 3 days and another for 2 days, and 10% of the remaining available hours are reserved for Scrum events. What is the planning capacity?

  1. A. 324 hours
  2. B. 330 hours
  3. C. 297 hours
  4. D. 294 hours

Correct answer: C. 297 hours

Available days = 60 - 5 = 55, i.e. 330 hours; reserving 10% leaves 297 hours. 324 ignores the leave, and 294 subtracts 10% of the full 360 instead of the available 330.