CS FundamentalsModerateAccenture · Capgemini
A 6-member team plans a 10-working-day sprint at 6 focus hours per person per day. One member is on leave for 3 days and another for 2 days, and 10% of the remaining available hours are reserved for Scrum events. What is the planning capacity?
- A. 324 hours
- B. 330 hours
- C. 297 hours
- D. 294 hours
Correct answer: C. 297 hours
Available days = 60 - 5 = 55, i.e. 330 hours; reserving 10% leaves 297 hours. 324 ignores the leave, and 294 subtracts 10% of the full 360 instead of the available 330.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- In a quarter a team made 40 production deployments. 6 of them caused incidents needing a fix or rollback, and restoring service took 9…
- A team wants estimates from several experts without anchoring on the loudest voice. A coordinator collects anonymous estimates, shares the…
- A program has 240 executable statements and the current suite covers 180 of them. A new test executes 40 statements, 25 of which were…
- A system is sized at 400 function points. The team's productivity is 8 function points per person-month and a person-month costs ₹1.5…
- Basic COCOMO for an organic project: Effort = 2.4 x KLOC^1.05 PM and Time = 2.5 x Effort^0.38 months. For 20 KLOC, roughly how many people…
- Using Weighted Shortest Job First (WSJF = cost of delay / job size), in what order should these be done? A: cost of delay 20, size 10. B…