CS FundamentalsHardTCS · Infosys · Cognizant
A system is sized at 400 function points. The team's productivity is 8 function points per person-month and a person-month costs ₹1.5 lakh. With a constant team of 5, what are the cost and the duration?
- A. ₹50 lakh, 8 months
- B. ₹60 lakh, 10 months
- C. ₹75 lakh, 8 months
- D. ₹75 lakh, 10 months
Correct answer: D. ₹75 lakh, 10 months
Effort = 400/8 = 50 person-months, so cost = 50 x 1.5 = ₹75 lakh and duration = 50/5 = 10 months. ₹50 lakh confuses effort with rupees.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Basic COCOMO for an organic project: Effort = 2.4 x KLOC^1.05 PM and Time = 2.5 x Effort^0.38 months. For 20 KLOC, roughly how many people…
- Using Weighted Shortest Job First (WSJF = cost of delay / job size), in what order should these be done? A: cost of delay 20, size 10. B…
- Midway through a project: planned value ₹150 lakh, earned value ₹120 lakh, actual cost ₹100 lakh. What is the project's status?
- Team A's velocity is 40 story points per sprint and team B's is 25. Both work on the same product with similar sprint lengths. What can…
- A release backlog has 200 story points. The team's velocity is a steady 25 points per sprint, but stakeholders add about 5 points of new…
- A code inspection proceeds at 150 lines per hour in the meeting with 4 inspectors present. How much meeting effort does inspecting 3,000…