Using Weighted Shortest Job First (WSJF = cost of delay / job size), in what order should these be done? A: cost of delay 20, size 10. B: 12, size 4. C: 30, size 20. D: 9, size 2.
- A. C, A, B, D
- B. D, B, A, C
- C. D, B, C, A
- D. B, D, A, C
Correct answer: B. D, B, A, C
WSJF: A = 2.0, B = 3.0, C = 1.5, D = 4.5, so the order is D, B, A, C. Ordering by cost of delay alone gives C, A, B, D - the trap WSJF is designed to avoid.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Midway through a project: planned value ₹150 lakh, earned value ₹120 lakh, actual cost ₹100 lakh. What is the project's status?
- Team A's velocity is 40 story points per sprint and team B's is 25. Both work on the same product with similar sprint lengths. What can…
- A release backlog has 200 story points. The team's velocity is a steady 25 points per sprint, but stakeholders add about 5 points of new…
- A code inspection proceeds at 150 lines per hour in the meeting with 4 inspectors present. How much meeting effort does inspecting 3,000…
- A function-point estimate and a COCOMO estimate for the same project differ widely. Which statement best explains why function points are…
- A team measures defect density after release. Release 1: 30 defects in 15 KLOC. Release 2 adds 10 KLOC of new code and has 26 defects, all…