CS FundamentalsHardCognizant · Scrum interview
Team A's velocity is 40 story points per sprint and team B's is 25. Both work on the same product with similar sprint lengths. What can you validly conclude?
- A. Team A is 60% more productive than team B
- B. Team B is padding its estimates
- C. The teams should be merged at an average velocity of 32.5
- D. Nothing about relative productivity, because each team calibrates its own story-point scale
Correct answer: D. Nothing about relative productivity, because each team calibrates its own story-point scale
Story points are relative to each team's own reference stories, so velocities are not comparable across teams; velocity is a planning tool for the same team only. Using it to rank teams also invites point inflation.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A release backlog has 200 story points. The team's velocity is a steady 25 points per sprint, but stakeholders add about 5 points of new…
- A code inspection proceeds at 150 lines per hour in the meeting with 4 inspectors present. How much meeting effort does inspecting 3,000…
- A function-point estimate and a COCOMO estimate for the same project differ widely. Which statement best explains why function points are…
- A team measures defect density after release. Release 1: 30 defects in 15 KLOC. Release 2 adds 10 KLOC of new code and has 26 defects, all…
- Activities (days; predecessors): P 5 (-), Q 6 (-), R 5 (P), S 5 (Q), T 4 (R, S). The manager can shorten only one activity by 2 days…
- Counting each simple condition separately (each 'and'/'or' adds one) and each loop header as one decision, what is the cyclomatic…