Team A's velocity is 40 story points per sprint and team B's is 25. Both work on the same product with similar sprint lengths. What can you validly conclude?

  1. A. Team A is 60% more productive than team B
  2. B. Team B is padding its estimates
  3. C. The teams should be merged at an average velocity of 32.5
  4. D. Nothing about relative productivity, because each team calibrates its own story-point scale

Correct answer: D. Nothing about relative productivity, because each team calibrates its own story-point scale

Story points are relative to each team's own reference stories, so velocities are not comparable across teams; velocity is a planning tool for the same team only. Using it to rank teams also invites point inflation.