A release backlog has 200 story points. The team's velocity is a steady 25 points per sprint, but stakeholders add about 5 points of new scope every sprint. How many sprints until the backlog is empty?
- A. 10 sprints
- B. 8 sprints
- C. 7 sprints
- D. 9 sprints
Correct answer: A. 10 sprints
Net burn = 25 - 5 = 20 points per sprint, so 200/20 = 10 sprints. 8 sprints ignores the scope growth that a burn-up chart would show as a rising top line.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A code inspection proceeds at 150 lines per hour in the meeting with 4 inspectors present. How much meeting effort does inspecting 3,000…
- A function-point estimate and a COCOMO estimate for the same project differ widely. Which statement best explains why function points are…
- A team measures defect density after release. Release 1: 30 defects in 15 KLOC. Release 2 adds 10 KLOC of new code and has 26 defects, all…
- Activities (days; predecessors): P 5 (-), Q 6 (-), R 5 (P), S 5 (Q), T 4 (R, S). The manager can shorten only one activity by 2 days…
- Counting each simple condition separately (each 'and'/'or' adds one) and each loop header as one decision, what is the cyclomatic…
- For the function below, which single call executes every statement (100% statement coverage)? python def f(a, n): total = 0 for x in a: if…