A release backlog has 200 story points. The team's velocity is a steady 25 points per sprint, but stakeholders add about 5 points of new scope every sprint. How many sprints until the backlog is empty?

  1. A. 10 sprints
  2. B. 8 sprints
  3. C. 7 sprints
  4. D. 9 sprints

Correct answer: A. 10 sprints

Net burn = 25 - 5 = 20 points per sprint, so 200/20 = 10 sprints. 8 sprints ignores the scope growth that a burn-up chart would show as a rising top line.