Midway through a project: planned value ₹150 lakh, earned value ₹120 lakh, actual cost ₹100 lakh. What is the project's status?

  1. A. Over budget and behind schedule
  2. B. Over budget and ahead of schedule
  3. C. Under budget and behind schedule
  4. D. Under budget and ahead of schedule

Correct answer: C. Under budget and behind schedule

CPI = EV/AC = 1.2 (under budget) and SPI = EV/PV = 0.8 (behind schedule). Comparing AC with PV directly (100 < 150) would wrongly suggest both are fine.