CS FundamentalsModerateAccenture · Capgemini
Midway through a project: planned value ₹150 lakh, earned value ₹120 lakh, actual cost ₹100 lakh. What is the project's status?
- A. Over budget and behind schedule
- B. Over budget and ahead of schedule
- C. Under budget and behind schedule
- D. Under budget and ahead of schedule
Correct answer: C. Under budget and behind schedule
CPI = EV/AC = 1.2 (under budget) and SPI = EV/PV = 0.8 (behind schedule). Comparing AC with PV directly (100 < 150) would wrongly suggest both are fine.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Team A's velocity is 40 story points per sprint and team B's is 25. Both work on the same product with similar sprint lengths. What can…
- A release backlog has 200 story points. The team's velocity is a steady 25 points per sprint, but stakeholders add about 5 points of new…
- A code inspection proceeds at 150 lines per hour in the meeting with 4 inspectors present. How much meeting effort does inspecting 3,000…
- A function-point estimate and a COCOMO estimate for the same project differ widely. Which statement best explains why function points are…
- A team measures defect density after release. Release 1: 30 defects in 15 KLOC. Release 2 adds 10 KLOC of new code and has 26 defects, all…
- Activities (days; predecessors): P 5 (-), Q 6 (-), R 5 (P), S 5 (Q), T 4 (R, S). The manager can shorten only one activity by 2 days…