Basic COCOMO for an organic project: Effort = 2.4 x KLOC^1.05 PM and Time = 2.5 x Effort^0.38 months. For 20 KLOC, roughly how many people are needed on average?
- A. About 5 people
- B. About 12 people
- C. About 56 people
- D. About 3 people
Correct answer: A. About 5 people
E = 2.4 x 20^1.05 ≈ 55.8 PM and D = 2.5 x 55.8^0.38 ≈ 11.5 months, so staff ≈ 55.8/11.5 ≈ 4.8, about 5. 12 is the duration in months and 56 the effort.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Using Weighted Shortest Job First (WSJF = cost of delay / job size), in what order should these be done? A: cost of delay 20, size 10. B…
- Midway through a project: planned value ₹150 lakh, earned value ₹120 lakh, actual cost ₹100 lakh. What is the project's status?
- Team A's velocity is 40 story points per sprint and team B's is 25. Both work on the same product with similar sprint lengths. What can…
- A release backlog has 200 story points. The team's velocity is a steady 25 points per sprint, but stakeholders add about 5 points of new…
- A code inspection proceeds at 150 lines per hour in the meeting with 4 inspectors present. How much meeting effort does inspecting 3,000…
- A function-point estimate and a COCOMO estimate for the same project differ widely. Which statement best explains why function points are…