Basic COCOMO for an organic project: Effort = 2.4 x KLOC^1.05 PM and Time = 2.5 x Effort^0.38 months. For 20 KLOC, roughly how many people are needed on average?

  1. A. About 5 people
  2. B. About 12 people
  3. C. About 56 people
  4. D. About 3 people

Correct answer: A. About 5 people

E = 2.4 x 20^1.05 ≈ 55.8 PM and D = 2.5 x 55.8^0.38 ≈ 11.5 months, so staff ≈ 55.8/11.5 ≈ 4.8, about 5. 12 is the duration in months and 56 the effort.