CS FundamentalsModerateInfosys · Wipro
A team wants estimates from several experts without anchoring on the loudest voice. A coordinator collects anonymous estimates, shares the spread and the reasons, and repeats rounds until the estimates converge. Which technique is this?
- A. Wideband Delphi
- B. Planning poker with open discussion only
- C. Analogy-based estimation
- D. Top-down (parametric) estimation
Correct answer: A. Wideband Delphi
Anonymous, iterative rounds with a coordinator are the hallmark of (Wideband) Delphi. Planning poker reveals cards simultaneously but is not anonymous; parametric models such as COCOMO use formulas, not experts.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A program has 240 executable statements and the current suite covers 180 of them. A new test executes 40 statements, 25 of which were…
- A system is sized at 400 function points. The team's productivity is 8 function points per person-month and a person-month costs ₹1.5…
- Basic COCOMO for an organic project: Effort = 2.4 x KLOC^1.05 PM and Time = 2.5 x Effort^0.38 months. For 20 KLOC, roughly how many people…
- Using Weighted Shortest Job First (WSJF = cost of delay / job size), in what order should these be done? A: cost of delay 20, size 10. B…
- Midway through a project: planned value ₹150 lakh, earned value ₹120 lakh, actual cost ₹100 lakh. What is the project's status?
- Team A's velocity is 40 story points per sprint and team B's is 25. Both work on the same product with similar sprint lengths. What can…