CS FundamentalsHardProduct-company DevOps interview
In a quarter a team made 40 production deployments. 6 of them caused incidents needing a fix or rollback, and restoring service took 9 hours in total across those 6. What are the change failure rate and the mean time to restore?
- A. 6%, 1.5 hours
- B. 15%, 0.225 hours
- C. 40%, 1.5 hours
- D. 15%, 1.5 hours
Correct answer: D. 15%, 1.5 hours
Change failure rate = 6/40 = 15%; time to restore averages over failures, 9/6 = 1.5 hours. Dividing 9 hours by all 40 deployments gives the wrong 0.225 hours.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A team wants estimates from several experts without anchoring on the loudest voice. A coordinator collects anonymous estimates, shares the…
- A program has 240 executable statements and the current suite covers 180 of them. A new test executes 40 statements, 25 of which were…
- A system is sized at 400 function points. The team's productivity is 8 function points per person-month and a person-month costs ₹1.5…
- Basic COCOMO for an organic project: Effort = 2.4 x KLOC^1.05 PM and Time = 2.5 x Effort^0.38 months. For 20 KLOC, roughly how many people…
- Using Weighted Shortest Job First (WSJF = cost of delay / job size), in what order should these be done? A: cost of delay 20, size 10. B…
- Midway through a project: planned value ₹150 lakh, earned value ₹120 lakh, actual cost ₹100 lakh. What is the project's status?