Activities (days; predecessors): A 3 (-), B 4 (A), C 2 (A), D 5 (B), E 3 (C), F 2 (D, E). What are the total float and the free float of activity C?

  1. A. Total float 4 days, free float 0 days
  2. B. Total float 0 days, free float 4 days
  3. C. Total float 4 days, free float 4 days
  4. D. Total float 7 days, free float 0 days

Correct answer: A. Total float 4 days, free float 0 days

Critical path A-B-D-F = 14 days. C: ES 3, EF 5, LF 9 (E must start by 9), so total float 4; but E can start at 5, so C's free float is 0 - the float belongs to the C-E chain and sits with E. 7 is C's late start, not its float.