Activities (days; predecessors): A 3 (-), B 4 (A), C 2 (A), D 5 (B), E 3 (C), F 2 (D, E). What are the total float and the free float of activity C?
- A. Total float 4 days, free float 0 days
- B. Total float 0 days, free float 4 days
- C. Total float 4 days, free float 4 days
- D. Total float 7 days, free float 0 days
Correct answer: A. Total float 4 days, free float 0 days
Critical path A-B-D-F = 14 days. C: ES 3, EF 5, LF 9 (E must start by 9), so total float 4; but E can start at 5, so C's free float is 0 - the float belongs to the C-E chain and sits with E. 7 is C's late start, not its float.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A product backlog has 210 story points left. The team's velocity has ranged between 25 and 35 points per sprint. What is the honest range…
- A 6-member team plans a 10-working-day sprint at 6 focus hours per person per day. One member is on leave for 3 days and another for 2…
- In a quarter a team made 40 production deployments. 6 of them caused incidents needing a fix or rollback, and restoring service took 9…
- A team wants estimates from several experts without anchoring on the loudest voice. A coordinator collects anonymous estimates, shares the…
- A program has 240 executable statements and the current suite covers 180 of them. A new test executes 40 statements, 25 of which were…
- A system is sized at 400 function points. The team's productivity is 8 function points per person-month and a person-month costs ₹1.5…