CS FundamentalsHardAccenture · Cognizant · Scrum interview

A product backlog has 210 story points left. The team's velocity has ranged between 25 and 35 points per sprint. What is the honest range forecast for the number of sprints still needed?

  1. A. 6 to 8 sprints
  2. B. 6 to 9 sprints
  3. C. 7 to 9 sprints
  4. D. 5 to 8 sprints

Correct answer: B. 6 to 9 sprints

210/35 = 6 sprints at best and 210/25 = 8.4, which needs 9 whole sprints at worst. Writing 8 truncates instead of rounding up; 7 would be the mean-velocity (30) figure.