CS FundamentalsHardAccenture · Cognizant · Scrum interview
A product backlog has 210 story points left. The team's velocity has ranged between 25 and 35 points per sprint. What is the honest range forecast for the number of sprints still needed?
- A. 6 to 8 sprints
- B. 6 to 9 sprints
- C. 7 to 9 sprints
- D. 5 to 8 sprints
Correct answer: B. 6 to 9 sprints
210/35 = 6 sprints at best and 210/25 = 8.4, which needs 9 whole sprints at worst. Writing 8 truncates instead of rounding up; 7 would be the mean-velocity (30) figure.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A 6-member team plans a 10-working-day sprint at 6 focus hours per person per day. One member is on leave for 3 days and another for 2…
- In a quarter a team made 40 production deployments. 6 of them caused incidents needing a fix or rollback, and restoring service took 9…
- A team wants estimates from several experts without anchoring on the loudest voice. A coordinator collects anonymous estimates, shares the…
- A program has 240 executable statements and the current suite covers 180 of them. A new test executes 40 statements, 25 of which were…
- A system is sized at 400 function points. The team's productivity is 8 function points per person-month and a person-month costs ₹1.5…
- Basic COCOMO for an organic project: Effort = 2.4 x KLOC^1.05 PM and Time = 2.5 x Effort^0.38 months. For 20 KLOC, roughly how many people…