A backlog contains: 'As a developer, I want to create the database tables for orders.' Which INVEST criterion does it most clearly fail, and why?

  1. A. Estimable; table creation cannot be estimated
  2. B. Small; it is too large
  3. C. Testable; databases cannot be tested
  4. D. Valuable; it is a technical layer task that gives no value to a user on its own, unlike a thin vertical slice such as 'customer can place an order'

Correct answer: D. Valuable; it is a technical layer task that gives no value to a user on its own, unlike a thin vertical slice such as 'customer can place an order'

Good stories deliver user-visible value end to end. Horizontal tasks such as 'create tables' only matter when combined with other layers, so they should be tasks inside a vertical story.