CS FundamentalsModerateCognizant · Accenture
A team cannot estimate a story because it depends on an unfamiliar payment API. It schedules a time-boxed 2-day investigation whose output is knowledge, not shippable code. What is this called in agile?
- A. A spike
- B. A hardening sprint
- C. A sprint zero
- D. Technical debt
Correct answer: A. A spike
A spike is a time-boxed research task to reduce uncertainty so the real story can be estimated. Its result is learning (and sometimes a throwaway prototype), not production code.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Match each change with its maintenance type. P: fixing a crash reported by users. Q: changing the app to work with a new OS version. R…
- Which pair of Lehman's laws of software evolution best explains why an old in-house ERP becomes steadily harder to change?
- An organisation predicts defect counts and review effectiveness from statistical process-control charts of its historical data, but does…
- In the ISO/IEC 25010 product quality model, which of these is NOT a sub-characteristic of maintainability?
- How many of these statements about Kanban are correct? 1. Kanban prescribes fixed-length iterations. 2. Kanban does not prescribe specific…
- Boehm's cost-of-change data suggests that fixing a requirements defect after release can cost far more than fixing it during requirements…