An organisation predicts defect counts and review effectiveness from statistical process-control charts of its historical data, but does not yet run a systematic programme of process innovation based on that data. Which CMMI maturity level does this describe?

  1. A. Level 2 - Managed
  2. B. Level 3 - Defined
  3. C. Level 4 - Quantitatively Managed
  4. D. Level 5 - Optimizing

Correct answer: C. Level 4 - Quantitatively Managed

Level 4 uses statistical and quantitative techniques to control process performance. Level 3 standardises processes across the organisation without quantitative control; Level 5 adds continuous improvement and innovation.