Risk scores are likelihood x impact, each rated 1-5. Feature A: 4 and 2. Feature B: 2 and 5. Feature C: 3 and 3. Feature D: 5 and 1. In what order should risk-based testing prioritise them?
- A. D, A, C, B
- B. B, C, A, D
- C. A, B, C, D
- D. B, A, C, D
Correct answer: B. B, C, A, D
Scores: A = 8, B = 10, C = 9, D = 5, so B, C, A, D. Ordering by likelihood alone gives D, A, C, B.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Running a regression suite manually takes 40 hours per cycle. Automating it costs 300 hours up front; afterwards each cycle needs 2 hours…
- In standard terminology, a programmer misreads the specification (1), which leads to a wrong comparison operator in the code (2), which…
- Which set of exit criteria is most appropriate for ending a system-test cycle?
- Before go-live, the operations team checks that backups restore correctly, failover works, monitoring alerts fire and the system can be…
- In session-based exploratory testing, what defines a session?
- Which statement about integration-testing strategies is correct?