A project has BAC = ₹500 lakh, PV = ₹240 lakh, EV = ₹200 lakh and AC = ₹250 lakh. If both cost and schedule performance are expected to keep influencing the remaining work, the forecast is EAC = AC + (BAC - EV)/(CPI x SPI). What is this EAC?

  1. A. ₹625 lakh
  2. B. ₹550 lakh
  3. C. ₹600 lakh
  4. D. ₹700 lakh

Correct answer: D. ₹700 lakh

CPI = 0.8 and SPI = 200/240 ≈ 0.833, so CPI x SPI ≈ 0.667 and EAC = 250 + 300/0.667 = ₹700 lakh. ₹625 lakh is BAC/CPI (cost only) and ₹550 lakh assumes the rest goes exactly to plan.