CS FundamentalsVery hardPMP-style · Accenture · Capgemini
A project has BAC = ₹500 lakh, PV = ₹240 lakh, EV = ₹200 lakh and AC = ₹250 lakh. If both cost and schedule performance are expected to keep influencing the remaining work, the forecast is EAC = AC + (BAC - EV)/(CPI x SPI). What is this EAC?
- A. ₹625 lakh
- B. ₹550 lakh
- C. ₹600 lakh
- D. ₹700 lakh
Correct answer: D. ₹700 lakh
CPI = 0.8 and SPI = 200/240 ≈ 0.833, so CPI x SPI ≈ 0.667 and EAC = 250 + 300/0.667 = ₹700 lakh. ₹625 lakh is BAC/CPI (cost only) and ₹550 lakh assumes the rest goes exactly to plan.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Last sprint, 6 developers working 10 days completed 30 story points. Next sprint 5 developers are available for 9 days each. Using the…
- A single-server queue (M/M/1) serves 10 requests per second. At 8 requests/s the mean response time W = 1/(μ - λ) is 0.5 s. What happens…
- 90% of a CI pipeline's run time is parallelisable tests and 10% is serial setup. Moving to 8 parallel runners, what overall speed-up does…
- A suite of 1,200 tests averaging 3 seconds each is split evenly across 6 parallel shards, and each shard needs 2 minutes of setup before…
- A cache answers 90% of reads in 2 ms; on a miss the read takes 50 ms in total (cache check plus database). What is the average read…
- Each web server handles 250 requests/s, but for headroom servers should run at no more than 70% of that. Peak load is 2,000 requests/s and…