According to the 2020 Scrum Guide, how many of these are true? 1. An Increment may be delivered to stakeholders before the end of the sprint. 2. The Sprint Review is a gate that must approve every release. 3. Product Backlog refinement is an ongoing activity, not a formal Scrum event. 4. The Scrum Master is accountable for the Scrum Team's effectiveness.

  1. A. 1
  2. B. 2
  3. C. 4
  4. D. 3

Correct answer: D. 3

1, 3 and 4 are in the guide. The Sprint Review is a working session to inspect the outcome and adapt, and 'should never be considered a gate to releasing value'.